J Street Water Main Replacement

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
WA6253
Status
Completed
Engineer
City of Grants Pass
Contractor
Stephen Stark Excavation, LLC
Construction Start
December 1, 2014
Completion Date
March 3, 2015
Final Contract Amount
$81,642.20
Description
This Project Consisted of the Installation of Approximately 650 Lineal Feet of 8" Ductile Iron Water Main, Installation of a Fire Hydrant and Miscellaneous Plumbing Work.