Laurel Street and Mary Street Water Main and Sewer Replacement

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
WA6360
Status
Under Construction
Engineer
City of Grants Pass
Contractor
Timber Mountain Construction
Construction Start
07/24/2023
Estimated Completion Date
09/08/2023
Contract Amount
$644,769.00
Description The Project Will Consist of The Installation of Approximately 6 LF of 8” Pvc Sanitary Sewer Pipe, 318 LF of 8” HDPE Sewer Pipe Bursting, 599 LF Of 12” PVC Sewer Pipe and Associated Appurtenances, 535 LF of 4” Sewer Laterals, the Reconnection of 7 Existing Sewer Laterals, 2 Air Relief Valves, 16 Potable Water Connections, 925 LF of 8” Water Pipe & Fittings And 1 Fire Hydrant. Also Included with the Project Will Be Landscape Restoration, Concrete Work and Asphalt Paving and Patching. 