Westholm Park Playground Drainage

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
LB6377
Status
Completed
Engineer
City of Grants Pass
Contractor
Pair - A - Dice Construction
Construction Start
07/18/2022
Completion Date
08/16/2022
Contract Amount
$53,997.00
Description This Project installed 708 LF of storm drain pipe, 12 cleanouts, 40 SF of concrete sidewalks, and a catch basin.