Dollar Mountain Trailhead Parking Area

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
LB6370
Status
Under Construction
Engineer
City of Grants Pass
Contractor
Robco, INC
Construction Start
06/20/2022
Estimated Completion Date
August 4, 2022
Contract Amount
$117,794.00
Description This project will consist of 96 tons of asphalt pavement, 360 SF of pervious concrete pavement, 141 SF of concrete sidewalk ramp, 96 LF of 3" storm drain pipe, parking lot striping, tree protection fencing, clearing and grubbing.

Project Documents