Sun Glo Drive Street Reconstruction

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
TR6372
Status
Completed
Engineer
City of Grants Pass
Contractor
CPI Acquisitions LLC
Construction Start
07/27/2020
Completion Date
10/30/2020
Contract Amount
$367,579.74
Description The project will consist of 61 Lineal Feet of 4" Sanitary Sewer lateral, 50 Lineal Feet of 4" Irrigation Pipe, 777 Lineal Feet of Storm Drain pipe and Associated Appurtenances. Also included will be Curb & Gutter, Sidewalks and Asphalt paving.

Project Documents