D and E Street Alley (Between 6th and 7th) Sanitary Sewer Replacement
Project Details
Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
SE6198
Status
Completed
Engineer
City of Grants Pass
Contractor
Robco, Inc.
Construction Start
September 9, 2019
Completion Date
October 8, 2019
Final Contract Amount
$105,837.42
Description
The Project Consisted of the Removal and Replacement of Approximately 212 Lineal Feet of 8” PVC Sewer Main, Associated Laterals, Concrete Valley Gutter, and Asphalt Patching.