Allen Creek Trail - Pedestrian Bridge North

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number LB4955
Status Completed
Engineer City of Grants Pass
Contractor Timber Mountain Construction, Inc.
Construction Start
July 20, 2018
Final Completion Date
November 30, 2018
Contract Amount
$229,679.05
Description This Project Installed an 8’ Wide Asphalt Path on Compacted Base and 48’ Precast Bridge.