Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
SE6156
Status
Completed
Engineer
City of Grants Pass
Contractor
Timber Mountain Construction, Inc.
Construction Start
June 18, 2018
Final Completion Date
June 28, 2018
Final Contract Amount
$57,348.75
Description
This Project Removed and Replaced Approximately 220 Lineal Feet of 8” PVC Sewer Main and Associated Laterals and Appurtenances. Included was Asphalt Restoration.