Number
TR6324
Status
Completed
Engineer
City of Grants Pass
Contractor
Copeland Paving, Inc.
Construction Start
September 25, 2017
Completion Date
November 20, 2017
Final Contract Amount
$269,239.00
Description
This Project consisted of Cold Plane Pavement Removal, Approximately 2367 Tons of Asphalt Paving, Associated Curb, Gutter and Miscellaneous Utility Adjustments.