G and H Street Alley (West of 3rd to 6th Street) Sanitary Sewer Replacement

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
SE6323
Status
Completed
Engineer
City of Grants Pass
Contractor
KOGAP Enterprises, Inc.
Construction Start
July 31, 2017
Completion Date
October 31, 2017
Final Contract Amount
$394,948.00
Description
The Project Removed and Replaced 30 Lineal Feet of 12” PVC Storm Drain, 859 Lineal Feet of 8” PVC Sewer Main, 106 Lineal Feet of 8” Ductile Iron, 350 Lineal Feet of 12” PVC Sewer Main and Associated Laterals and Appurtenances. Also included was Asphalt Alley Restoration.