Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
WA6253
Status
Completed
Engineer
City of Grants Pass
Contractor
Copeland Paving, Inc.
Construction Start
March 15, 2017
Final Completion Date
August 1, 2017
Final Contract Amount
$363,744.50
Description
The Project Consisted of the Installation of Approximately 1480 Lineal Feet of 8” Water Line and 230 Lineal Feet of 8” Sanitary Sewer Main and Associated Appurtenances. Also Associated with the Project was Asphalt Patching, Curb, Gutter and Sidewalk Replacement.