Savage Street Bridge

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
TR6165
Status
Completed
Engineer
ZCS Engineering, Inc.
Contractor
Timber Mountain, Inc.
Construction Start
May 16, 2016
Completion Date
March 17, 2017
Final Contract Amount
$899,325.90
Description
Removal of a Large Existing Concrete Culvert, Installation of a New 40’ Span Bridge on a Driven Pile Foundation, Installation of Concrete Fish Passage Structure within a Fish Bearing Stream, Replacement of Existing Sanitary Sewer and Water Pipe Section, Installation of (2) Water Quality Storm Drain Catch Basins and Associated Storm Drain Pipe, and Associated Roadway Surface Improvements. Construction will Require Engineered Shoring for Bridge Foundation Installation and the Contractor Must Comply with Project Related Permits (E.G. In-Water Work an a Fish Bearing Stream).