Number LB6280
Status Completed
Engineer City of Grants Pass
Contractor Moser Paving, Inc.
Construction Start
July 6, 2016
Completion Date
July 15, 2015
Contract Amount
$14,328.00
Description The project consisted of the installation of approximately 578 LF of asphalt path on re-compacted base.