J and K Street Alley (East and West of Pine Street) Sanitary Sewer Replacement

Project Name: “J” and “K” Street Alley (East and West of Pine Street) Sanitary Sewer Replacement
Project Number: SE6064
Status: Completed
Engineer: City of Grants Pass
Contractor: KOGAP Enterprises, Inc.
Construction Start: February 29, 2016
Completion Date: May 18, 2016
Final Contract Amount: $120,317.57
Project Description: This Project Consisted of the Removal and Replacement of Approximately 1065 Lineal Feet of 8” PVC Sewer Main and Associated Laterals and Appurtenances.