Lincoln Road Half Street Improvements

Project Name: Lincoln Road Half Street Improvements
Project Number: TR6075
Status: Completed
Engineer: ZCS Engineering
Contractor: ROBCO, Inc.
Construction Start: March 1, 2016
Completion Date: June 27, 2016
Contract Amount: $438,869.30
Project Description: Consisted of the Installation of Approximately 300’ of Various Sized Storm Drain Pipe and Associated Catch Basins and Manholes, 200’ of D.I.P. Water Main and Associated Appurtenances, 2200’ of Curb And Gutter, 11,000 Sq. Ft. of Sidewalk, 3000 Sq. Ft. of Driveway Approaches and 6 Sidewalk Ramps, and 300 Tons of Asphalt Paving. Included Were Miscellaneous Striping and Landscaping.