Terry Lane Street Improvements

Project Name: Terry Lane Street Improvements 
Project Number:  TR6295
Status: Construction Punch List Items
Engineer: City of Grants Pass
Contractor: Copeland Paving, Inc.
Construction Start: October 19, 2015
Estimated Completion: December 5, 2015
Contract Amount: $224,576.50
Project Description: This Project will Include the Installation of Approximately 380 Lineal Feet of Various Sizes of Storm Drainage and Assorted Appurtenances, Installation of 550 Lineal Feet of 6” Schedule 40 PVC Irrigation Pipe, Installation of Approximately 420 Lineal Feet of 8” Ductile Iron Water Main and Appurtenances, 1250 Lineal Feet of Curb and Gutter, 7000 Square Feet of Sidewalk, Pedestrian Ramps and Driveway Approaches, 1020 Tons of Aggregate Road Base Course and 400 Tons of Asphalt Pavement.  Also Included will be Various Fence Relocations, Light Pole Base Installation and Mailbox Support Relocation.