Morrison Park Pedestrian Path

Project Name:Morrison Park Pedestrian Path 
Project Number: LB6190
Status:Completed
Engineer:City of Grants Pass
Contractor:Copeland Paving, Inc.
Construction Start: August 10, 2015
Completion Date: August 31, 2015
Final Contract Amount:$43,033.00
Project Description:This Project Installed Approximately 171Tons of Asphalt Path on Compacted Base.
Reinhart/Morrison Park Pedestrian Paths
Morrison Park