Lincoln School Pedestrian Path

Project Name: Lincoln School Pedestrian Path
Project Number:LB6143
Status:Completed
Engineer:City of Grants Pass
Contractor:Copeland Paving, Inc.
Construction Start:July 8, 2013
Final Completion Date:August 8, 2013
Final Contract Amount:$13,344
Project Description:This Project Installed an Asphalt Path in Varying Widths from 8' to 10'. (Approximately 175 Tons)
Lincoln School Pedestrian Path
Lincoln School Pedestrian Path 2