K Street Sewer

Project Name:K Street Sewer
Project Number:SE6176
Status:Completed
Engineer:City of Grants Pass
Contractor:Timber Mountain Construction, Inc.
Construction Start:April 5, 2013
Final Completion Date:April 26, 2013
Final Contract Amount:$40,575.50
Project Description:This Project Replaced Approximately 385 Lineal Feet of 8 Inch Sewer Main and Associated Laterals and Appurtenances.
K Street