Project Name: Hubbard Lane Widening
Project Number: TR4924
Status: Completed
Engineer: Hardey Engineering & Associates
Contractor: Timber Mountain Construction, Inc.
Construction Start: April 15, 2013
Final Completion Date: November 4, 2013
Final Contract Amount: $1,046,114.80
Project Description: This Project Installed New Storm Drainage and Associated Appurtenances; Approximately 4200 Lineal Feet of Curb, Gutter, and Sidewalk; Rehabilitation of Approximately 2100 Lineal Feet of Road Base Section and Installation of New Asphalt Resurfacing with Associated Striping for Bike Lanes. Also Included was all Work Involved in the Widening of the Sand Creek Box Culvert.