South Middle School Bike / Pedestrian Path

Project Name: South Middle School Bike / Pedestrian Path
Project Number:LB6143
Status:Completed
Engineer:City of Grants Pass
Contractor:ROBCO, Inc.
Construction Start:August 20, 2014
Completion Date: September 11, 2014
Contract Amount:$26,945.55
Project Description:This Project installed 337 tons of 1/2" Level 2 Dense Graded HMAC for an 8' Wide Bike/Pedestrian Path.