South Middle School Bike / Pedestrian Path

Project Name: South Middle School Bike / Pedestrian Path
Project Number: LB6143
Status: Completed
Engineer: City of Grants Pass
Contractor: ROBCO, Inc.
Construction Start: August 20, 2014
Completion Date: September 11, 2014
Contract Amount: $26,945.55
Project Description: This Project installed 337 tons of 1/2" Level 2 Dense Graded HMAC for an 8' Wide Bike/Pedestrian Path.