E & F Street Alley Sanitary Sewer Replacement

Project Name: E and F Street Alley (5th to 6th Street) Sanitary Sewer Replacement
Project Number: SE6064
Status: Completed
Engineer: City of Grants Pass
Contractor: McBee Construction, LLC
Construction Start: September 22, 2014
Completion Date: October 21, 2014
Final Contract Amount: $92,262.38
Project Description: Removed and Replaced Approximately 310 Lineal Feet of 8" PVC Sewer Main and Associated Laterals and Appurtenances.