E & F Street Alley Sanitary Sewer Replacement

Project Name: E and F Street Alley (5th to 6th Street) Sanitary Sewer Replacement
Project Number:SE6064
Status:Completed
Engineer:City of Grants Pass
Contractor:McBee Construction, LLC
Construction Start:September 22, 2014
Completion Date:October 21, 2014
Final Contract Amount:$92,262.38
Project Description:Removed and Replaced Approximately 310 Lineal Feet of 8" PVC Sewer Main and Associated Laterals and Appurtenances.