Drury Lane Street Improvements 2014 

Project Name: Drury Lane Street Improvements 2014
Project Number: TR6115
Status:  Construction Punch List Items
Engineer: ZCS Engineering
Contractor: Copeland Paving, Inc.
Construction Start:  January 5, 2015
Estimated Completion: November 1, 2015
Contract Amount: $1,282,198.25
Project Description: Removal and Replacement of an Existing Bridge, Installation of Approximately 2150 Lineal Feet of Varying Sizes of Storm Drain Pipe, Installation of Approximately 1220 Lineal Feet of 12” Water Main and 200 Lineal Feet of 8” Water Main and Associated Appurtenances, Installation of Approximately 3,400 Lineal Feet of Curb And Gutter, Approximately 2300 Square Feet of Sidewalk and Driveway Approaches and Associated Sidewalk Ramps, Cold Plane Removal of the Existing Asphalt Surface, Rebuilding the Road Base and Installing Approximately 1500 Tons of New Asphalt Road Surface. Also Included will be Landscaping, Striping, Miscellaneous Fencing, Irrigation Relocation and Lighting Installation.