Ramsey and Grandview Intersection Reconstruction

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
TR8413
Status
Under Construction
Engineer
City of Grants Pass
Contractor
Roxy Ann Rock, Inc.
Construction Start
December 4, 2017
Estimated Completion
December 23, 2017
Contract Amount
$63,775.00
Description
Installation of Approximately 700 SF of Sidewalk, 145 SF of Sidewalk Ramps, 135 LF of Curb and Gutter; 780 LF of Valley Gutter, Pedestrian Island and Associated Asphalt Paving.