NE C Street Water Main Relocation

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
WA6249
Status
Completed
Engineer
City of Grants Pass
Contractor
KOGAP Enterprises, Inc.
Construction Start
November 28, 2016
Completion Date
June 19, 2017
Final Contract Amount
$314,569.50
Description
The Project Consisted of the Installation of Approximately 645 Lineal Feet of 12” Water Line and 720 Lineal Feet of 8” Sanitary Sewer Main and Associated Appurtenances. Also Included were Asphalt Patching, Miscellaneous Storm Drain Pipe and Appurtenances and Curb, Gutter and Sidewalk Replacement Associated with the Project.