School - Park Construction Portola Park Phase 2

Project Details

Project Details, including: project name, number, status, engineer, contractor, start, completion, final amount, and project description
Number
LB6326
Status
Completed
Engineer
City of Grants Pass
Contractor
Copeland Paving, Inc.
Construction Start
August 15, 2016
Final Completion Date
September 8, 2016
Final Contract Amount
$25,472.14
Description
This Project Installed Approximately 1150 Lineal Feet of 8’ Wide Pedestrian Path at Portola Park in Grants Pass, Oregon. Path Consisted of 175 Tons of 2” Thick ½” Dense Graded, Level 2 Asphalt Mix Over 300 Tons of 6” Thick Compacted ¾” – 0” Rock Base. Excavation was Performed By Others.